Details
Total work based on primary contract
38,880 m³/day
Average Flow
9.55 mg/day
BOD 5
150 mg/day
TSS
Facts
Type of Treatment | Indirection Filtration |
Location | Mianeh |
Start date | 2008 |
Duration | 30 Months |
Client | Ministry of Energy – Azerbaijan Regional Water Co. |
Consultant | Abran Consulting Engineers |