Details
Total work based on primary contract
40,000 m³
Earthwork
20,000 m²
Formwork
300,000 kg
Steelwork
5,500 m³
Cast in place concrete
Facts
Project Description | Design , Procurement , Construction and Operation of Mehrabad & Rudehen Wastewater Treatment Plant |
Capacity | 3022.5 m³/day by activated sludge method |
Location | Rudehen , Tehran Province |
Start date | 2016 |
Duration | 36 months |
Client | Tehran East Water and Wastewater Company |
Consultant | Pars Peyab Consulting Engineers |