Khoshkeh Floodway Canal

Brief

Construction of concrete canal in 3,000 mm width and 2,000 m length and related settling basins in 350 m length for collecting the surface water of eastern watershed of Saadat Abad – Darakeh Floodway.

Details

Total work based on primary contract

230,000

Earthwork

3,200

Formwork

990,000 Kg

Steelwork

19,000

Cast in place concrete

Facts

Type of structure Reinforced concrete canal
Length 2,000 m
DimensionsW: 4,000 mm   H: 3,000 mm
Type of structure Reinforced Concrete Reservoir
Length 200 m
Number2
Capacity 20,000 m³
LocationWest of Tehran
Start date1995
Duration15 Months
Client Tehran Municipality
Consultant Engineering and Improvement Organization of Tehran city.
Main works
  • Construction of reservoir basins in 20,000 m³ capacity along Evin-Darakeh Floodway
  • Construction of reservoir basins in 20,000 m³ capacity along khoshkeh Floodway
  • Construction of concrete canal along khoshkeh Floodway
  • Construction of cross bridge along khoshkeh Floodway and exit road of Darakeh
  • Construction of bottom and embankment of canal
  • Construction of settling basin ramps
  • Construction of the walls of settling basin
  • Construction of gabions behind of the walls of settling basin
  • Construction of bridge of canal
  • Construction of drop and levelling of canal